New electricity pylons on the north flank of the Rigi

Section of the 380-kV high-voltage Lavorgo-Mettlen power line to be renovated

(lifePR) (Olten, )
This summer Atel Transmission Ltd. is planning to replace 28 supports for the existing Lavorgo-Mettlen power line on the section between Arth and Küssnacht am Rigi, along the north flank of the Rigi. Work will start in early May and is scheduled for completion at the end of October 2008. The cost of replacing the pylons will be around CHF 15 million.

Renovation work on the 380-kV line, on the 8.5-kilometer long section in the canton of Schwyz between Arth and Küssnacht am Rigi, is part of the overall upgrade of the power line between Amsteg and Mettlen. All pylons along the line, which is more than 60 years old, will be replaced by new supports. The new steel pylons comply with the stricter requirements imposed on high-voltage lines over the past few decades. The line axis remains unchanged. At an average height of 64 meters, the new supports will be somewhat taller than the old pylons. This will achieve two objectives: The greater distance from the ground and buildings will offer better protection against non-ionising radiation. And the higher pylons will improve the operational reliability of the 380-KV line. Operational reliability is particularly important since the line is an essential element on the North-South axis of the Swiss transmission grid. The line will also make an important contribution to energy supplies in central Switzerland.

Plans for renovation were officially published in the spring of 2002. Atel Transmission Ltd. made several modifications in response to various appeals and concerns. The plans to renovate the line section were approved by the Swiss Federal Office for Energy in March 2008, and construction is scheduled to begin on 5 May 2008.

During the construction work from mid-May to the end of October 2008, the 380-kV Lavorgo-Mettlen line will be temporarily routed via the parallel power line operated by CKW. The cost of replacing the pylons will be around CHF 15 million.

The 380-kV power line between Lavorgo and Mettlen was first built in 1948/49. Despite extensive maintenance since then, corrosion and ageing have now reached the point where the pylons need to be replaced. Atel Transmission Ltd. is implementing the replacement project in phases. The first phase was launched in 1989, and in the summer of 2006 the company replaced 17 supports between Sisikon and Ingenbohl. Over the next few years the supports on both sections of Ingenbohl and Arth in the canton of Schwyz, as well as the section between Küssnacht am Rigi and Udligenswil in the canton of Lucerne, will be replaced.

Alpiq Holding AG

Atel Holding Ltd (Atel Group) is Switzerland's leading energy provider, active throughout Europe.

Founded in 1894, Atel focuses on the two core businesses of production-based energy trading and energy services. The group of companies, domiciled in Olten, currently employs a staff of around 9000 and generated revenue of CHF 13.5 billion in 2007. The main markets for the Energy segment are Switzerland, Italy, Germany, France and countries in Central and Eastern Europe.

Products and services range from portfolio management and group energy supplies to energy derivatives, option contracts and the establishment of distribution concepts based on partnerships.

Trading and sales are supported by a number of proprietary hydraulic and thermal power stations in Switzerland, Italy, Hungary, Norway and the Czech Republic as well as an extensive transmission grid in Switzerland. With its Energy Services segment, Atel delivers all the technical services related to energy (electricity, gas, oil, and biomass) and its applications (power, light, cooling and heating, communications and security). Atel is among the leading providers of energy services in Switzerland and Germany. Since the end of 2007 the Atel Group has also included the former Motor-Columbus Group. Further information are available at www.atel.eu

Für die oben stehenden Stories, das angezeigte Event bzw. das Stellenangebot sowie für das angezeigte Bild- und Tonmaterial ist allein der jeweils angegebene Herausgeber (siehe Firmeninfo bei Klick auf Bild/Titel oder Firmeninfo rechte Spalte) verantwortlich. Dieser ist in der Regel auch Urheber der Texte sowie der angehängten Bild-, Ton- und Informationsmaterialien. Die Nutzung von hier veröffentlichten Informationen zur Eigeninformation und redaktionellen Weiterverarbeitung ist in der Regel kostenfrei. Bitte klären Sie vor einer Weiterverwendung urheberrechtliche Fragen mit dem angegebenen Herausgeber. Bei Veröffentlichung senden Sie bitte ein Belegexemplar an service@lifepr.de.
Wichtiger Hinweis:

Eine systematische Speicherung dieser Daten sowie die Verwendung auch von Teilen dieses Datenbankwerks sind nur mit schriftlicher Genehmigung durch die unn | UNITED NEWS NETWORK GmbH gestattet.

unn | UNITED NEWS NETWORK GmbH 2002–2024, Alle Rechte vorbehalten

Für die oben stehenden Stories, das angezeigte Event bzw. das Stellenangebot sowie für das angezeigte Bild- und Tonmaterial ist allein der jeweils angegebene Herausgeber (siehe Firmeninfo bei Klick auf Bild/Titel oder Firmeninfo rechte Spalte) verantwortlich. Dieser ist in der Regel auch Urheber der Texte sowie der angehängten Bild-, Ton- und Informationsmaterialien. Die Nutzung von hier veröffentlichten Informationen zur Eigeninformation und redaktionellen Weiterverarbeitung ist in der Regel kostenfrei. Bitte klären Sie vor einer Weiterverwendung urheberrechtliche Fragen mit dem angegebenen Herausgeber. Bei Veröffentlichung senden Sie bitte ein Belegexemplar an service@lifepr.de.